Tutorial Step 13: Level Resources
By default, OmniPlan responds dynamically to changes in your project by Automatic Leveling resources. If you would prefer to control when the project is leveled, you can disable automatic leveling in the Project menu.
Two tasks are assigned to use the resource Me and the resource Glue at the same time.
Click the Level button
in the toolbar, then deselect the Don't schedule any task before date checkbox and click OK.
The second task moves to avoid the resource usage conflict.